Summary
Library Director Tina Herbal introduced a space‑utilization study and architect Corey Sharp of FEH Design proposed reconfiguring the library (lighting, children's and teen areas, study spaces), possible upper‑level addition (~3,800 sq ft) and a cost range of roughly $3M–$4M; staff asked for council feedback and did not seek funding yet.
Get email alerts on the Libraries topic
No spam. Unsubscribe anytime.
The Pella City Council heard a staff presentation and a consultant report outlining options to update and expand the city library.
Library Director Tina Herbal explained the study's origin (a Carnegie Foundation $10,000 gift and library board support) and said the effort was to determine how the facility can meet community needs. Architect Corey Sharp (FEH Design) presented space‑use findings and alternatives, including improved entry and circulation, family restrooms, a reinvigorated children's program area, acoustic screening, a potential second level of approximately 3,800 square feet, and repurposing lower‑level storage for a makerspace or heritage room. Sharp summarized estimated cost ranges and said the comprehensive option was roughly "$3 to $4 million" in construction costs (not including soft costs). "So when you add all these things up... you're somewhere between 3 and $4,000,000," Sharp said.
Staff emphasized this is a planning concept only and not a request for funding; they asked council for feedback on priorities and on pursuing fundraising and grant options. The council discussed possible sequencing (small‑scale furnishings and lighting upgrades first) and asked staff to return with additional cost breakdowns and public‑engagement plans if the council wishes to advance the concept.