2nd Avenue South project: paving done from 16th to 15th; engineer reports 43% complete
Summary
An engineering update showed paving from 16th to 15th complete and the 2nd Avenue South project about 43% complete; staff will check ADA ramp slopes and a roadway hump noted by a councilor.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
An engineering representative told the council that paving is complete between 16th and 15th streets and that the 2nd Avenue South project is roughly 43% complete, with remaining work including driveways, sidewalks and storm work. The engineer said some pay items have been completed but not yet entered into the paperwork, which affects the percent‑complete figures.
Council members requested follow‑up on ADA ramp slopes at the southwest corner of 16th and 2nd and asked staff to review a reported pavement hump at an intersection to ensure the design intent was met. The engineer agreed to revisit the plans and report back at the next meeting.
Staff emphasized the shared goal of reconciling the design intent with field conditions and completing final driveway and sidewalk approaches before fully opening the remaining sections to two‑way traffic.