Contractor outlines Phase 4 water‑main work, says project will run through year
Summary
Contractor Johnson Davis told the Ocean Ridge commission the water‑main Phase 4 contract started at the end of July and will continue through the rest of the year; the work will improve water flow, fire protection and replace hydrants. The contractor said flagging operations and resident mailers paid by the contractor will limit surprises and that sidewalks damaged during work will be replaced.
Get email alerts on the Water Main topic
No spam. Unsubscribe anytime.
Johnson Davis project manager Clark Scribe introduced his team and said the Phase 4 water‑main contract began at the end of July and is expected to continue through the rest of the year. Meredith Cruz, the firm's public‑relations lead, told the commission, “So, the water main improvements will enhance the water flow and the fire protection and also replace the fire hydrants on the west side of the roadway.”
Cruz described a three‑phase schedule, two‑week flagging operations and daily cone placement to indicate continuing work. The contractor said it has been doing door‑to‑door outreach and will fund a town mailer to notify residents; Clark Scribe said the team will post monthly progress updates on the town website. On concerns about sidewalks, the contractor said any sidewalks damaged during construction will be replaced, and they will coordinate daily packing up during certain flagging operations to reduce disruption.
Commissioners asked about lane closures during the December high season; the contractor said the work should be wrapped up by then but cautioned weather and unforeseen underground conditions could cause delays. The commission thanked the team and said staff will request periodic updates if needed.