District and consultants outline next steps: surveys, potholing, engineer's report and outreach
Summary
Consultants said the project needs additional survey work, potholing and geotechnical investigations, plus negotiations with Solvang, the county and the Regional Water Quality Control Board; an engineer's report and rate study will follow to set parcel assessments.
Get email alerts on the Process Next Steps topic
No spam. Unsubscribe anytime.
Wallace Group and district staff told attendees the 30% design is an intermediate step and more field work is required to refine costs and design details. The team plans survey work to locate septic tanks, potholing to verify utility locations and geotechnical investigations to reduce construction unknowns before preparing the engineer's report that will feed the assessment and rate study.
Staff said they will pursue additional grants and county assistance while preparing the assessment engineer's package and are targeting early 2027 for a property-owner vote once parcel-specific costs are known. Staff also encouraged public outreach and education to increase homeowner understanding and acceptance of whichever option the board forwards.