Staff seeks RFP for electrical distribution study; 7 MW from KMEA secured for September
Summary
Staff told the commission that paperwork is complete for 7 megawatts from KMEA for September and outlined plans for an electrical distribution study (mapping, arc‑flash, switchgear work) with an RFP to be presented for approval.
Get email alerts on the Electric Distribution topic
No spam. Unsubscribe anytime.
Staff said all documentation with KMEA is in place to deliver 7 megawatts of additional power for Gardner City in September and that the city has the allocation on its first bill from the power provider. “KMEA, all the paperwork's been submitted for the enter or the electric rate study,” the staff member said, and indicated the city will begin an electric-rate study around Sept. 1.
Separately, staff said they are preparing an RFP for a comprehensive electrical distribution study to map the system, perform an arc‑flash analysis and identify upgrades (switchgear, bus work, pad and spacing) required to accommodate the new Substation 1 transformer; staff expects to present the RFP to the commission for approval.