Substation 4 transformer draws $243,000 in tariffs; Substation 1 needs LTC repairs and distribution upgrades

Gardner City Utility Advisory Commission · August 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told the commission that tariffs added about $243,000 to a transformer purchase from Korea for Substation 4, and flagged arcing in the Substation 1 load-tap changer with estimated repairs and longer-term distribution upgrades required to support a 35 MVA unit.

Staff told the commission that City Council had approved tariff adjustments on the Substation 4 transformer purchased from Korea, adding roughly $243,000 in additional tariffs; staff said whether a tariff refund will be available is not yet known. “It ended up by $243,000 of additional tariffs for that transformer since we bought that transformer from Korea,” the staff member said.

Separately, staff described internal arcing detected in the Substation 1 load‑tap changer (LTC) through oil‑gas analysis (high ethylene) and estimated about $20,000 for immediate repairs, noting that permanent distribution and breaker upgrades will be required if the city intends to fully utilize a 35 MVA transformer at Substation 1. Staff said the city is preparing to stage transformers and consider swaps to avoid unnecessary delivery if possible.