Construction at Heartland reaches substantial completion; district details punchlist and costs
Summary
The superintendent reported the district's construction project is at substantial completion, with punchlist and warranty work underway. Project expenses and contract figures were shared, including certified construction claims of $468,388.87 to Hausmann Construction.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Superintendent Jeremy Klein told the board Sept. 8 that construction on the district project has reached substantial completion and that administrators are working through punchlist and warranty items. The report noted training on integrated HVAC controls (Trane & Control Logic) remains to be completed and that access control and security-camera components are largely functional, with a few loose ends to tie up.
Financial materials in the packet show $11,589,215.75 expensed to date against a comprehensive project budget of $12,307,364.00; certified construction claims included in the consent agenda totaled $468,388.87 to Hausmann Construction Inc. The report also said HCDC planned to move into the new space Sept. 8, and that the district expects a $25,000 return from Hausmann for reinstalled playground equipment to be removed and replaced next summer.