Staff outlines utility relocation for Rock Creek stormwater project; flags service disruptions
Summary
City staff described plans to relocate utilities (including Evergy poles) as part of the Rock Creek stormwater project and said pole moves will produce short service interruptions that Evergy will notify customers about.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City staff described utility relocation work needed for the Rock Creek stormwater project, including relocating overhead utilities tied to roughly nine Evergy poles that sit in dedicated easements.
Brent Morton said the relocation is necessary to allow creek channel stabilization, bridge replacement and sanitary‑main consolidation, and that the city is working to acquire permanent easements before Evergy sets new pole locations. He emphasized sequencing so poles are not moved multiple times during later construction phases.
On customer impact, Morton said utility cutovers will cause temporary outages and that Evergy has a notification process for affected customers: "But I think the standard is between 4 and 6 hours when they cut them over because they leave the old stuff live until they power up the new ones." Staff said additional easements are expected to appear in September and that relocation work will begin after easements are acquired and coordination is complete.
Committee members asked about bridge condition ratings and whether canopy pruning would be included; staff replied Evergy maintains its overhead lines and the city will perform invasive creek excavation work requiring separate coordination.