Supervisors approve final plans for Channelworth (SF-49) bridge replacement

Jackson County Board of Supervisors · August 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved final plans and signatures for the SF-49 Channelworth bridge replacement project; county engineer said right-of-way was acquired and plans are ready for letting to meet a November letting schedule.

County engineer Jaden Shackle told the board that all necessary right-of-way for the Channelworth (SF-49) bridge replacement had been secured and that final bridge plans were complete and due for signature so the project could meet its November letting schedule.

"Plans have proceeded, and in order for us to hit November of letting bridal plans are due today, and they are now here. Done. Ready for DOT approval and signature," Shackle said. Supervisor Mike Steiner moved to approve the final plans; Nan Flago seconded and the board voted in favor to approve the SF-49 Channelworth bridge replacement plans. Shackle said it was satisfying to see a DOT-funded project come to fruition.