Board approves contractor change requests for high school addition
Summary
Trustees approved three contractor change requests—CR-32 (de-watering), CR-28R (HVAC equipment price increase), and CR-44 (canopy footing)—to be paid from contractor contingency funds for the Bond 2022 high school additions; motion passed 7-0.
Get email alerts on the Construction Change Requests topic
No spam. Unsubscribe anytime.
The board approved the district's use of contractor contingency funds to cover three change requests on the high school addition. The minutes state: "Motion was made by Nikki Yarnall, seconded by Eli Ramos, duly put and carried to approve the following change requests: - CR 32 De-watering - CR 28R HVAC Equipment price increase - CR44 Canopy footing. Motion carried. Vote 7-0."
Board members recorded unanimous approval for the change requests. The minutes do not list dollar amounts for each request; staff previously briefed the board on contingency needs during construction updates and will manage funding in line with the district's bond oversight procedures.