Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Development Updates topic

No spam. Unsubscribe anytime.

Planning staff updates commissioners on Canyon Bay, Mountain Bay and Granite Ridge projects

Willard City Planning Commission · August 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told commissioners Canyon Bay has returned a development agreement and agricultural easement for review, Mountain Bay is working on a water agreement and master meter tied to the Barricka Water Conservancy District, and Granite Ridge is awaiting an executed agreement with Staker Parsons before moving phase 6 work forward.

Planning staff provided a status update on several active developments. The Canyon Bay development returned a largely complete development agreement and agricultural easement; staff reported it includes nearly 100 pages of exhibits and remains under legal review. Mountain Bay is negotiating a water agreement: the development must build a master meter and infrastructure that will be dedicated to the city and the master meter will be tied to the Barricka Water Conservancy District for water supply and billing.

Granite Ridge remains on pause pending an executed agreement with Staker Parsons related to Hall Road and easement work; staff said the developer has not returned the signed documents and certain phase-6 activities, including gravel-mining, are blocked until agreements and fixes are in place. Staff also described technical constraints for basement construction in some phases—properties in one plan are shown at about three feet above the waterline and would require engineered dewatering systems to permit basements.