Commission approves contractor payments and loan-disbursement paperwork for Osage County Sewer District project

Osage County Commission · August 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved invoices and a contractor pay application for Osage County Sewer District No. 1 and authorized loan-compliance assurances for project C20-2083-01 (American Iron & Steel and Davis-Bacon requirements), pending legal review and final CDBG adjustment.

Ben Kramer of Kramer Consulting updated commissioners on the Sewer District No. 1 project and presented contractor pay requests and loan-disbursement paperwork tied to project number C20-2083-01.

Kramer told the board that the contractor application and related documentation are prepared and that CDBG funds expected to reduce the county draw will be finalized later. The chair moved to approve Kramer Consulting invoice #42259 in the amount of $9,685 and the contractor's application for payment No. 5 in the amount of $22,798.29 to be paid from Osage County Sewer District No. 1 fund; the motion passed.

The commission also moved and approved the loan-recipient compliance assurances addressing American Iron & Steel and Davis-Bacon wage-rate requirements for the same project, pending legal review. The chair said signatures could be provided once staff receives updated CDBG numbers and counsel’s review.

Why it matters: The votes advance closeout activity on a multi-year sewer project and release contractor funds while preserving conditions for federal loan compliance (wage and domestic steel provisions). The approvals were recorded as contingent on final CDBG disbursement figures and legal sign-off.

What the board recorded: Motion to approve loan compliance assurances (American Iron & Steel; Davis-Bacon) and to authorize payment of the two listed invoices and contractor payment application, all as presented and pending minor updates.