Court approves extra $304 for JP2 desk; facilities report chiller, HVAC, election storage updates
Summary
Facilities director Rodney Floyd briefed the court on Justice Center chiller leak repair, AHU reprogramming, LifeCheck sensor installation at the jail and election storage cleanup; the court approved increasing the authorized JP2 desk purchase by $304.14 to a total of $3,304.14.
Get email alerts on the County Facilities topic
No spam. Unsubscribe anytime.
Facilities Director Rodney Floyd told the court the Justice Center chiller will require a coil replacement and that staff have reprogrammed AHU units at the Justice Center Annex to begin balancing the building and improve cooling efficiency.
The court approved an additional $304.14 on a previously authorized desk purchase for JP2 in the Justice Center Annex. "There's a motion before the court by commissioner Philip Cox, seconded by commissioner Michael Rasca to allow Rodney Floyd to go ahead and make the purchase of the JP 2 debt additional desk, for the amount of $3,304.14, which is an increase of $304.14 from the previous authorization," Judge Fowles read. Commissioners voiced thanks to the facilities team for ongoing warranty work and punch-list responsiveness from contractor MBC.
Why it matters: Repairs and equipment purchases are funded from building contingency and are intended to maintain operations at the Justice Center and the annex. The desk purchase was approved as an incremental increase to previously authorized spending.
Next step: Facilities will schedule the chiller coil replacement and continue warranty closeout with MBC; purchases will proceed under the approved authorization.