Ladd approves Change Order #3, final payment for Main Avenue sidewalk; final contract $121,825

Ladd Village Board · December 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Engineer Adam Ossola presented Change Order #3 and the final payment request from Gillan Construction; trustees approved a $6,513.50 change order that raises the project total to $121,825.00 and leaves $40,768.23 remaining to be paid.

Engineer Adam Ossola presented the final payment request and Change Order #3 for the Main Avenue Sidewalk Project, explaining a completion-date update and cost changes submitted by Gillan Construction. Trustee Bernie Victor moved to approve the change order and final payment; Trustee Molly Thrasher seconded and the motion carried unanimously.

The change order increased the contract by $6,513.50, bringing the total final cost to $121,825.00. The minutes note a remaining amount to be paid of $40,768.23. The Board's vote approved acceptance of the final work and authorization of final payment per the engineer's recommendation.