Michiana schedules water-main work tied to $620,000 grant; pump installation after Labor Day

Village of Michiana Council · August 9, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Councilmember Mike Mumper said Merritt Engineering is finalizing plans for a Creek-area water project funded by a $620,000 grant; the new pump will be installed after Labor Day and the mains work could start in October and take two to three weeks.

Councilmember Mike Mumper told the Village of Michiana council that Merritt Engineering is completing plans for a water project on Creek and that he hopes work will begin in October. He said the new pump will be installed after Labor Day.

Mumper said the water-main portion of the work is estimated to take two to three weeks and that asphalt repairs could be finished by mid-November. He indicated these items are part of a $620,000 grant that funds the projects, but did not specify the grant source or a final project schedule at the meeting.