Commission approves up to $50,000 to bring permanent power to new fairgrounds building

Putnam County Board of County Commissioners · August 4, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Deputy Administrator JR Grimes told commissioners the pad-mount transformer and conduit work for permanent three-phase power will cost roughly $35,000 (FPL hard cost) plus about $15,000 for trenching and conduit; the board approved up to $50,000 from general-fund reserves to proceed so contractors can complete work.

Putnam County authorized up to $50,000 from general-fund reserves to install permanent three-phase electrical service at the new fairgrounds building so contractors can proceed with remaining work.

Deputy Administrator JR Grimes (speaker 28) explained that because the new building currently lacks a demand profile the utility required an upfront pad-mount transformer and conduit build-out. Grimes said an FPL "hard cost" estimate for the transformer and wire was about $35,000 and installation and trenching for conduit would be roughly $15,000, producing a round figure near $50,000. The board discussed whether the utility could later reimburse the county once demand materialized; Grimes said he would inquire with FPL.

On motion, commissioners approved up to $50,000 from general-fund reserves to fund the electrical work, with staff to pursue potential reimbursement or grant options as the project moves forward.