Council approves wastewater screen procurement; engineer says six-month lead time

City of Jenkins City Council · August 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved contracting Hubert Technologies for a wastewater treatment plant screen and moved several KIA-funded requisitions; the city engineer said the screen has a six-month lead time and may not arrive until late January.

The council approved a requisition and award related to the Jenkins wastewater treatment plant screen, with the chair noting the screen purchase is covered under a grant. The meeting packet identified the vendor award to Hubert Technologies; the motion to approve the screen requisition passed by voice vote.

Harold, the attending engineer, told the council the screen has a lengthy manufacturing lead time. "There's a 6 month lead time on that screen," he said, and added the screen likely will not be received until the end of January; staff plan to issue bid documents late this fall so contractors can prepare submittals and be ready when the equipment arrives.

Why it matters: procuring the screen is a critical step in the wastewater-treatment improvements and affects project schedule and contractor readiness. The council also later approved a KIA-funded wastewater improvement requisition (requisition certificate number 3) for $45,337 at the same meeting, which staff said is for the wastewater treatment improvements.

What’s next: staff will proceed with procurement activities and present subsequent requisitions and construction schedules to council as deliveries and approvals progress.