County road superintendent details projects, material cost increases and timelines

Elko County Regional Transportation Commission · July 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Elko County Road Superintendent Dennis Price told the commission the county completed a mag program covering about 150 miles, is seeing mag material costs rise to roughly $138 per ton, and outlined chip-seal/slurry projects and a nearly complete 1.78-mile Lucky Nugget paving project. He said a preconstruction meeting was set for July 31.

Dennis Price, Elko County Road Superintendent, gave a detailed status update on county road work. He said the county completed its mag program and "we're right at a 150 miles of road that we treat now." Price noted rising costs: "I think we're paying $138 a ton now" for mag material, up from under $100 a few years ago.

Price outlined scheduled work: a preconstruction meeting on July 31 for upcoming chip/seal and slurry projects; planned work on Sundance Drive (county portion), the paved portion of Last Chance Road, South Fork Road (type 2), Lucky Nugget Road (majority, stopping where new paving exists), Lower Lee Road (type 2), and Palace Parkway in the Spring Creek Association area (type 3 slurry). He also reported that the Lucky Nugget paving project (about 1.78 miles) is substantially complete with striping done and only punch-list items remaining. No formal action was requested on the county updates.