Public asks about Wells Gym roof delay; staff says machine delivery and vendor licensing caused pause
Summary
A public commenter on the internal capital committee asked why the Wells roof work had paused; staff said Garland Roofing supplies materials and the contractor needs a bending machine and vendor licensing to proceed, with the machine expected within days.
Get email alerts on the Roofing Project topic
No spam. Unsubscribe anytime.
Public commenter Beth Savadra, who the chair identified as a member of the internal school district capital committee review, asked why roofing activity at Wells had been delayed after cones were placed and no crews appeared. She said she had seen the issue raised at a school board meeting and wondered whether the delay related to the trash contract or other matters.
Matt Stolke explained that "Garland Roofing supplies the materials for the project" and that the contractor needed a bending machine to form metal roofing components; that machine was expected by the end of the week or next week and work would resume. Stolke also said a contractor was not a licensed vendor for Garland, which contributed to schedule adjustments.