Commissioners approve final change order for solids-handling project after debate over cumulative change orders

Butte-Silver Bow Council of Commissioners · August 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved final change order No. 6 with Swank Enterprises for a $4.4M ARPA-funded solids-handling and dewatering project. Commissioners questioned $633,000 in change orders on the contract and sought process improvements, while public-works staff said the county requested and funded the additions from ARPA.

Commissioners on Aug. 5 placed on file final change order No. 6 with Swank Enterprises for the solids handling and dewatering improvements project. Commissioner Fisher raised concerns that the project had $633,000 in change orders on an original $4.4 million base bid — a percentage he described as too high — and urged a review of bidding and contracting procedures.

Director Neri responded that the work was ARPA-funded and the change orders represented county-requested improvements that made the project better; he said ratepayers at the Metro Sewer plant were not charged and the state did not require returning the funds. The council moved to concur and place the communication on file; the clerk recorded a unanimous 12–0 vote.

The exchange highlighted a recurring commissioner focus on cumulative change orders and procurement oversight; staff acknowledged the concern and said they would continue to refine processes and justify additions in the project record.