Council votes to withdraw purchase offer for 122 Rose after structural engineer's report
Summary
A structural engineer's report identified foundation, roof and bracing concerns for 122 Rose Avenue; council voted to withdraw the purchase agreement based on those findings and requested appraisal/next steps be handled through follow-up actions.
Get email alerts on the Building Purchase topic
No spam. Unsubscribe anytime.
Staff presented a structural engineer's report on 122 Rose Avenue that highlighted significant roof, foundation and bracing issues and recommended more detailed review. Council members expressed concern about the extent of work needed and whether an appraisal was appropriate before purchasing. After discussion, a motion to withdraw the purchase agreement "based on the engineering report" was made and passed.
Members said the engineer's observations, including possible need for tearing off and rebuilding roof components and foundation repairs at the northwest corner, raised the city's potential exposure and cost beyond what was acceptable without further investigation. Council asked staff to stop the purchase process and to pursue any necessary follow-up steps including cost estimates and appraisal if the city reconsiders the property.