Poulsbo council hires independent reviewer for Kitsap County WWTP estimates; $19,240.96 task order approved
Summary
The council authorized a $19,240.96 Parametrix task order for an independent review of 60% cost estimates for the Central Kitsap Wastewater Treatment Plant upgrade to clarify Poulsbo’s share of costs amid rising project estimates.
Get email alerts on the Infrastructure Wastewater topic
No spam. Unsubscribe anytime.
Poulsbo authorized a task order of $19,240.96 to hire Parametrix (expert David Bershauer) for an independent review of Central Kitsap Wastewater Treatment Plant 60% cost estimates. Staff said the review will help determine which costs the city should pay — Poulsbo owns approximately 20% of the plant’s capacity — and which items (septage-related facilities or capacity increases) should be excluded from the city’s share.
"We own 20% of the capacity of the treatment plant so technically we're responsible for 20% of the cost," staff member Diane said, noting the project estimate has grown from about $65 million two years ago to $149 million in the county CIP. Council members emphasized value engineering and asked about any conflicts of interest; staff said Parametrix has previously worked for the city but is not involved in the county treatment‑plant work and will act as an independent reviewer.
Council approved the Parametrix task authorization by voice vote and authorized the mayor to sign the task order. Members noted the county is engaged in value‑engineering work and that the city’s review can inform coordination and potential revisions to the ILA if needed.