Sportsplex expansion: foundations in, addition slightly behind schedule
Summary
A contractor/consultant update said foundations and slabs are poured and interior plumbing is largely complete; the addition is about a week to 10 days behind schedule and the board reviewed exterior finishes and finish samples.
Get email alerts on the Capital Project Sportsplex topic
No spam. Unsubscribe anytime.
Andrew (presenter, speaker 7) updated the board on progress at the Sportsplex project, reporting poured foundations, new interior slabs, completed plumbing runs to the addition, and the start of masonry work for concession and bathroom areas. "We're somewhere between a week to 10 days behind on the addition in accordance with our kickoff schedule," he said, and added that subcontractors and good weather may allow the team to make up time.
Board members discussed exterior finishes and color samples to match the nearby school gym; Andrew recommended a medium bronze roof-edge and driftwood insulated metal panels to complement the school. He invited the board to walk the site and said on‑site representation and biweekly meetings are keeping the project coordinated. The update concluded with agreement to continue biweekly meetings and to schedule any requested walkthroughs.