District unveils timelines for CTE Center (target 2030) and phased Environmental Science Center (soft launch 2027, full phase by 2029)
Summary
Facilities staff presented site, design and permitting timelines for two major bond 2025 projects: a CTE Center proposed for the Versailles site with a tentative August 2030 opening, and a two‑phase restoration and new‑build plan for the Environmental Science Center with phase 1 renovation targeted for August 2027 and phase 2 new building targeted for September 2029.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District facilities staff outlined schedules and site constraints for two bond‑funded projects: the Career and Technical Education (CTE) Center and the Environmental Science Center.
For the CTE Center, staff identified a district‑owned Versailles site near Greenville and Walnut Avenues (about 43 acres, roughly 25.7 acres buildable). The high‑level schedule targets an August 2030 opening, with about 20 months allocated to design and permitting and roughly 24 months for construction. Staff said city approvals and zoning are factored into the schedule and that board approval is expected in September 2028 before a late‑2028 ground‑breaking. Facilities noted the district’s debt capacity constrains how many major projects can be sold at once.
On the Environmental Science Center, staff said the existing building is in a special flood hazard area (floodway), which restricts rebuilding on the same footprint. The recommended approach is a two‑phase plan: phase 1 renovate the existing footprint (design and permitting ~5 months, construction ~8 months) with a soft launch planned for August 2027; phase 2 would add a new building on a nearby non‑floodplain site and finish by September 2029, connecting the two facilities with outdoor programming and trails. Staff emphasized that renovation is feasible but new construction on the floodway is not financially practical.