District advances HVAC Phase III planning and schedules main gym remodel for Summer 2026
Summary
Superintendent J. Henry reported the district is advancing Phase III of an HVAC project with contractor walkthroughs this week and authorized Lunsford Architects to begin planning a main gym remodel (paint, floor, bleachers) for Summer 2026.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Superintendent J. Henry told the board that after a pre-construction meeting with Lunsford Architects and Heartland Mechanical Contractors, Facilities Supervisor B. Gunter will walk Phase III of the district's HVAC project this week with Heartland's foreman to determine move-out and summer work sequencing. Henry described Phase III as involving different sections of the building and requiring planning for classroom furniture/supplies placement and clean-up scheduling.
Henry also said he has authorized Lunsford Architects to begin planning for a main gym remodel — including paint, floor and bleacher work — targeted for Summer 2026, and that feasibility studies for additional projects aligned with Board priorities will commence as soon as possible.