Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Soundside Projects topic

No spam. Unsubscribe anytime.

Soundside Road projects split across phases; Phase 3 pumping station costly but central to system

Nags Head Board of Commissioners · August 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff described three Soundside Road phases: Phase 1 (36-inch trunk at ~$750,000) ranked third; Phase 2 connects Ridgeview Way to existing infrastructure; Phase 3 is a pumping station moved north (cost about $1.8M) that links multiple projects and can provide water-quality benefits when paired with infiltration.

David described Soundside Road Phase 1 as a relatively high-cost trunk installation (~$750,000) intended to reduce ponding along the corridor by installing a 36‑inch diameter trunk network. He said Phase 1 ranked third because of frequent flooding and numbers of residences affected.

On Phase 3, David said the pumping station originally shown at Deering Street was relocated north to an undeveloped parcel; staff estimates the land purchase and pump system will make Phase 3 expensive (about $1.8 million) but it would connect other projects and allow a comprehensive drainage solution for the area. Board members agreed that Phase 3’s infiltration/water‑quality benefits are important for grant eligibility.