Houston council approves major contracts, payments for outdoor recreational complex
Summary
The Houston City Council approved multiple contracts and payments tied to the Houston Outdoor Recreational Complex, including a $733,760.27 building package and several construction and electrical bids, moving the project forward with combined vendor spending in the hundreds of thousands.
Get email alerts on the Houston Outdoor Recreational Complex topic
No spam. Unsubscribe anytime.
The Houston City Council on July 20 approved a series of vendor payments and contract awards to advance the Houston Outdoor Recreational Complex, including a $733,760.27 pre‑engineered building package.
Alderman Don Romines moved to approve payment to American Realty & Development, LLC for a Varco‑Pruden pre‑engineered metal building package "in the amount of $733,760.27," a motion the council carried with four yes votes. The council earlier approved payments to Central Missouri Excavation Contracting, Inc. for installation and grading ($92,570.51) and to TOG Industrial Services for 1" base rock ($2,884.92).
The council also awarded an electrical contract for the complex to 5B Electric, LLC for $259,870.00 and a plumbing contract to Amick Built, LLC for $47,500.00; both awards were approved by council vote. City officials recorded additional equipment purchases tied to operations and construction: a utility bed for the water department truck ($12,943.00) and a light pole change‑out contract ($42,504.00).
The Nut Graf: These approvals represent the bulk of vendor contracting and equipment purchases recorded at the July 20 meeting and move the recreational complex through procurement and installation phases. Funding sources for each contract were recorded in motions but granular line‑item sources beyond general capital improvement accounts were not specified in the minutes.
Council members who voted in favor included Alderman Fred Stottlemyre, Alderwoman Sheila Walker, Alderwoman Ann Tottingham and Alderman Don Romines; Alderwoman Chelsye Scantlin was recorded as not present. No dissenting votes were recorded at the meeting.
The council tabled adoption of a separate Building Permit Application pending a Utility Committee meeting; a public hearing on building codes was scheduled for Sept. 28, 2026.