Council approves budget transfers to replace obsolete water treatment control panel

City of Amsterdam Common Council (Committee of the Whole) · June 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized a budget amendment to replace an obsolete SCADA filter-panel at the water plant, citing a not-to-exceed replacement estimate (~$328,575) and proposed transfers of roughly $279,732 this fiscal year to avoid a water rate increase.

City staff told the council that the filter-panel and associated electrical/software installed in 2010 are no longer supported and require replacement. The SCADA team provided a cost estimate and staff proposed shifting budget lines so the work can be paid from the current fiscal year rather than by raising water rates.

The transcript records a not-to-exceed estimate of approximately $328,575 for replacement hardware and software; the formal resolution read into the record described budget decreases in contingency and other lines and an increase to the filter-panel replacement account of $279,732. A staff member said the new control system should be more efficient and easier to operate than the 15-year-old equipment it replaces.