Council transfers $63,654.95 to replace failed DPW bus-garage HVAC unit
Summary
Council approved a fund transfer to replace a failed air handler at the DPW bus garage with a new 120,000 BTU unit at a cost of $63,654.95 under Resolution 2627-15.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Council approved Resolution 2627-15 to transfer funds for a DPW bus-garage HVAC replacement after staff reported the existing unit failed and must be removed and replaced. The resolution lists the replacement as a new 120,000 BTU unit at a cost of $63,654.95.
A staff member summarized the problem: "The Scribe air condition unit has failed, and therefore, to repair it is $63,645." Councilors asked whether the unit could be repurposed and whether the bus garage would be kept long term; staff responded that the bus garage remains in service and a new building may be pursued later.
The council moved and recorded its approval; the clerk called the roll and recorded ayes from several alderpersons.