Commission weighs generator upgrade, transfer switch and power‑management options for county facilities
Summary
Staff presented generator sizing and replacement options for a county facility — winter peak loads prompted a recommendation for a 150 kW generator; trenching, transfer switch and time-delay costs could push the full package toward $150,000 and staff will return with firm bids.
Get email alerts on the Facilities Power topic
No spam. Unsubscribe anytime.
Facility staff and the county's engineering contact reviewed specifications for replacing an aging backup generator at a county facility. A recent load analysis showed a winter peak of about 168 kVA (151 kW) and a summer peak of approximately 120 kVA (108 kW); staff said a 150 kW generator was being recommended.
The discussion included transfer‑switch specifications and the need for time‑delay devices to stagger large compressor startups. Staff estimated +/- $122,000 for a generator and indicated additional trenching, meter work and trenching for the meter could bring the total package toward $150,000. Commissioners asked staff to obtain competitive prices and to return with a full package price and warranty details before approval.
Commissioners also discussed siting the generator relative to a fenced operations area and ensuring required meter placement and trenching avoid operational conflicts; staff will coordinate final siting, meter arrangements and any necessary coordination with the gas utility and railroad right‑of‑way.