Village awards OSLAD phase‑1 sealcoating bid to SKI Sealcoating for $563,667.08
Summary
Following Chamlin and Associates' bid review, trustees accepted SKI Sealcoating & Maintenance as the low bidder for the OSLAD phase‑1 project at $563,667.08; the vote was 5-0 with Trustee Barry absent.
Get email alerts on the Oslad Award topic
No spam. Unsubscribe anytime.
Chamlin and Associates presented results for the OSLAD phase‑1 grant bidding process. Trustees voted to accept SKI Sealcoating & Maintenance as the low bidder and awarded the phase‑1 contract in the amount of $563,667.08.
Trustee Adams moved to accept the low bid and Trustee Price seconded; the motion carried on a 5-0 roll call vote with Trustee Barry absent. The award is tied to the OSLAD grant project scope presented by Chamlin and Associates at the meeting.