Board hears facilities update; superintendent urges prioritizing HVAC, stage rigging and lighting
Summary
The district reported completed elementary tile work, demolition of art rooms and library spaces, an expected high school canopy completion by May/June, and a recommendation to prioritize HVAC in the multipurpose room plus stage rigging/lighting for upcoming bids.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
District officials told the Board that elementary tile work is complete and that demolition is finished in the middle/high school art rooms and elementary school library as part of Phase 1 and Phase 2 construction work.
Superintendent Ryan Pacatte and Ryan Dempsey of Campus Construction reviewed work to date and recommended prioritizing HVAC improvements in the multipurpose room and stage rigging and lighting. The minutes note the high school canopy is expected to be complete around May or June and that playground work is on hold until weather permits. The Board discussed bid alternates and asked the OACM group to consider putting prioritized items out to bid.
No formal funding decisions were made at the Feb. 10 meeting; trustees were briefed on progress and asked staff to return with next steps for bidding and budgeting.