Commission approves $126,700 change order to pave Stumptown Road to reduce cemetery dust
Summary
The commission approved Change Order #2, adding about 2,200 linear feet of 3‑inch asphalt paving on Stumptown Road for $126,700 to reduce dust near the cemetery and complement previous cemetery paving.
Get email alerts on the Roads topic
No spam. Unsubscribe anytime.
Commissioners approved a $126,700 change order to add paving and reconditioning of approximately 2,200 linear feet of Stumptown Road, a project Trihydro described as intended to reduce dust near the cemetery and complement prior work inside the cemetery.
"This project includes paving and reconditioning of the existing road base and it's approximately 2,200‑linear feet in length..." Trihydro representative Sara Cline told the commission, describing a scarify and repack sequence and a 3‑inch asphalt lift to be applied after Road Department base preparation. The motion to approve Change Order #2 carried 4‑0.