Board accepts PSCOC award and technical correction for Chaparral roof coating; district share about $131,000

Deming Public Schools Board of Education · August 7, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board accepted a PSCOC award and a technical-correction memo that changes Chaparral Elementary's scope from an initial design-phase roof-replacement letter to a roof-coating award; staff said the total project is about $488,000 and the district share will be roughly $131,000 once the corrected award letter arrives.

Deming Public Schools accepted the PSCOC award letter and an accompanying technical-correction memo that clarifies the Chaparral Elementary project is for a roof coating rather than a full replacement, and the board moved to accept the initial letter plus the correction so staff can begin work when the corrected award is issued.

Superintendent (functional) explained the confusion and the practical effect: the original award letter appeared to fund design for a replacement but staff submitted a technical correction so the award will cover a coating. The superintendent said the total project cost will be about $488,000 and the district's share will be about $131,000 when PSCOC issues the corrected award: "In total, this the cost of this new project is gonna be, for the coating. The total cost overall is gonna be, $488,000, but only our part will only be a $131,000 when that comes back in." Staff also said they will hire a roof observer and that PSFA will issue the purchase order for the work, which may include additional soft costs.

The board voted unanimously to accept the award letter and technical correction and to proceed with procurement and oversight steps as staff return corrected award documentation.