Engineer reports boil order, temporary repairs and timeline for water‑tower work
Summary
Paul, the city engineer, told the council that point repairs for the sanitary sewer were completed, a cracked cap on an asbestos‑cement line near 4th & Park triggered a boil order that required temporary repairs, and valve and coating work on the water tower is scheduled with an aim to restore full service by mid‑September.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
Paul, the city engineer, opened his update on sewer and water projects by saying, “The point repairs have been, completed as part of the forestry project to get CIPP, started.” He told the council that point repairs were made to allow the cured‑in‑place pipe (CIPP) contractor to begin lining work and that the project currently appears to be a bit under earlier estimates, with roughly $12,000 expected to remain for final pay requests.
Paul described a recent water service interruption that led to a boil‑water notice. A cap on an asbestos‑cement water line near the 4th‑and‑Park intersection cracked, allowing high‑pressure discharge and necessitating an overnight response from staff and the fire department. Crew members performed temporary work to restore water service; Paul said permanent fittings and full valve work would occur at the next scheduled shutdown. He also briefed the council on water‑tower work, saying valve repairs would begin soon, interior coating mid‑month and exterior coating to follow, targeting a return to full service by mid‑September.
Paul recommended adding more properly placed restraint joints and additional shutoff valves at intersections to reduce the need for town‑wide shutdowns during future projects. The council asked several operational questions about sequencing for the 4th Street water‑main work and the engineer confirmed contractors plan to complete a bore under the highway this week to connect new mains across the corridor.