Resident questions $131,000 re‑added features for Mountain View Park pickleball project
Summary
A member of the public challenged a change order for Mountain View Park pickleball courts, noting a 90% estimate originally ~ $1 million and a later $131,000 re‑insertion of features; council approved the pulled consent item after brief comment.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
Greg Oliver, who had pulled Item 6 from the consent calendar, urged the council to scrutinize a change order for the Mountain View Park pickleball project and asked whether park funds might be better spent on housing, homelessness services or library repairs. Oliver said the 90% engineering estimate was about $1,000,000, features previously removed were later re‑added at an estimated $131,000 and questioned whether the project scope warranted the added expense.
Council allowed public testimony and then voted to approve the change order motion (the consent motion had been pulled for public discussion); the motion passed 5–0. "If the project was alright without those features in it, then maybe that $131,000 could have gone towards helping low cost housing, the homeless, helping the hungry," Oliver said while asking the council to consider alternatives and transparency about dedicated park funds.