OBI demolition and parking work delayed; move-in access set for July 20–24

BELLVILLE INDEPENDENT SCHOOL DISTRICT · July 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Dr. Coopersmith said demolition at O'Bryant Intermediate is in progress but AT&T equipment and additional abatement have delayed the parking-lot and road work until Fall 2026; move-in access is scheduled for July 20–24 and TESCO furniture deliveries for July 20–31.

Dr. Coopersmith provided an update on capital projects, reporting that demolition for O'Bryant Intermediate (OBI) is under way but that reconstruction of the OBP parking lot and road will be delayed until Fall 2026 because of an AT&T system located in the planned reconstruction area and additional abatement work required for full demolition.

He also flagged weather-related delays affecting work at the Bellville High School student parking lot. The minutes record access for move into OBI is scheduled for the week of July 20–24, and TESCO furniture deliveries across all campuses are scheduled July 20–31. Supporting documents are available in the BoardBook online.