Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Developers tell joint meeting sewer and utility costs limit where housing can be built

Joint Special Meeting — City of East Wenatchee & Douglas County Board of Commissioners · January 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A written public comment and staff analysis cited sewer distance, undersized lines and pumping needs as key constraints that make many UGA parcels financially or logistically infeasible for higher-density development.

The developer's written submission and staff analysis both emphasized that sewer availability and utility capacity are central constraints on deliverable housing in the UGA.

The written comment from KTS Development said municipal sewer service is often not reasonably close and that extending or upsizing sewer lines, building pumping facilities, or meeting irrigation-district water line requirements can make otherwise well-located parcels financially infeasible. The letter concluded "Scarcity is real — it is not an illusion," arguing that focusing growth where infrastructure exists will reduce costs and improve housing attainability.

Community Development staff presentation framed similar trade-offs: staff recommended prioritizing upzoning in areas "near existing utilities" to avoid the high cost of extending sewer and other necessary upgrades. Commissioners and councilmembers discussed these constraints as they considered where to concentrate higher-density zoning and which lands to include in any UGA expansion.

No new funding or engineering commitments were authorized at the meeting; staff will return with prioritized maps and recommendations that take infrastructure feasibility into account.