Reeder Construction reports steady progress on Brock ISD multipurpose student center
Summary
Reeder Construction told the board most structural steel is complete, about half the sheeting is done, roofing installed on practice rooms, fire sprinkler and electrical rough-in underway, and HVAC equipment is scheduled to arrive.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Raj Paide of Reeder Construction told trustees the multipurpose student center is progressing: most structural steel is completed, painting has begun and roughly 50% of exterior sheeting is finished; exterior doors are expected to arrive in the coming weeks.
Paide added that roofing has been installed on practice rooms, fire sprinkler installation and electrical rough-in have begun, all concrete work is complete with some insulation underway, and HVAC equipment is scheduled to arrive soon. The update was presented as part of the superintendent's report; no vote was required.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.