City manager reports multiple infrastructure and planning updates, schedules pre-construction meetings
Summary
City Manager Roseann Peralta updated the council on several capital projects and timelines, including a June 3 pre-construction meeting for Camino del Llano and Picard going out to bid on June 4. She also reported work on Well 9 funding discussions with USDA and ongoing PD building engineering.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City Manager Roseann Peralta provided a series of project updates during the May 18 meeting, naming specific upcoming dates and procurement steps.
Peralta said a purchase order is pending for work on N. 1st Street near the pedestrian bridge and that a Notice of Obligation for the Great Blocks project should be forthcoming. The Camino del Llano pre-construction meeting is scheduled for June 3 and Picard will go out to bid on June 4; a 3rd Street pre-construction meeting is being scheduled. She said staff is working with USDA for additional funding for Well 9, that a building across the way should be ready June 1, and that engineers are working on the police department building.
Councilor Steven L. Holdman asked about sandbags and a deeper pond on the south side of Camino del Llano. Peralta said the street crew is assessing ponds and that the city will contact contractors about sewers before the monsoon season. The updates span multiple public works projects the council will monitor as design and procurement proceed.
Speakers: [{"name":"Roseann Peralta","role_title":"City Manager","affiliation_type":"government","first_reference":{"block_id_start":"SEG 002"}},{"name":"Steven L. Holdman","role_title":"Councilor","affiliation_type":"government","first_reference":{"block_id_start":"SEG 003"}}]
Provenance: {"transcript_segments":[{"block_id_start":"SEG 003","block_id_end":"SEG 003","evidence_excerpt":"City Manager Roseann Peralta stated: 1. N. 1st Street on other side of pedestrian bridge, we are waiting on PO for this. 2. Spoke with engineers for the Great Blocks project and the Notice of Obligation should be coming forward soon. 3. Camino del Lanno pre-con meeting is scheduled for June 3rd. 4. Picard out to bid on June 4th. 5. 3rd street project pre-con is being scheduled. 6. Well 9 Daniel working with USDA for additional funding. 7. Building across the way should be ready June 1st. 8. Working with engineers on PD building, more to come regarding this.","reason_code":"topicintro"},{"block_id_start":"SEG 003","block_id_end":"SEG 003","evidence_excerpt":"Questions for City Manager from Governing Body: Councilor Holdman asked about sandbags Camino del Llano on south side regarding the pond it looks deeper. Ms. Roseann advised the street crew is working on all the ponds.","reason_code":"topicfinish"}]}