Aquilla ISD trustees hear progress and drainage concerns on bond construction
Summary
School officials told the board that doors, hardware and theater lighting are installed, band-hall acoustics work has begun and drainage issues were found between the new building and the ag building.
Get email alerts on the Bond Project topic
No spam. Unsubscribe anytime.
Board President Will Pinner opened the May 18 meeting with a construction update on the district's bond projects. District staff reported that exterior doors, an overhead door and related hardware have been installed, concrete work is being finished, and theater/gym lighting and basketball goals are in place.
Superintendent Dr. David Edison and staff said band hall acoustics work has started and track lighting has been installed in the art room. Interior door framing has begun, but staff flagged drainage issues between the new building and the agricultural building that will require further review and corrective work. The report did not include a dollar figure for addressing the drainage problem or an estimated completion date.