Commissioners authorize $102,725.50 change order for Brownfield river‑benching project

Hancock County Commissioners · January 29, 2026

Summary

The board approved Change Order #1 with Buckeye Elm Contracting for $102,725.50 to complete Brownfield river‑benching on the north bank of the Blanchard River, citing glass found in soil; staff said grant funds are available and an additional $25,000 change order from CEC is expected.

The Hancock County Commissioners on Jan. 29 approved Resolution #75-26 to execute Change Order #1 with Buckeye Elm Contracting, LLC, adding $102,725.50 to the contract for a State of Ohio Brownfield Environmental Remediation river‑benching project along the north bank of the Blanchard River. Phil Johnson told the board the change order resulted from an unexpected volume of glass in the excavated soil; the contract completion date was extended through Jan. 31, 2026.

Kaysie Penzinski told commissioners there are funds available within the project grant to cover the change order and that the county expects an additional change order of approximately $25,000 from CEC. Phil said he believes the landfill charged for removal of the contaminated soil but did not provide a final accounting at the meeting. The board approved the change order on a 3-0 vote.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source