Administration building plumbing underway; practice-field soil reused to level pad

Flatonia ISD Board of Trustees · February 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

An SZS Architecture representative told trustees plumbing work has started on the administration building; soil from the band practice field was repurposed to level the building pad and the project manager said the schedule remains on pace.

At the Feb. 12 meeting, Abigail LaRussa of SZS Architecture updated the board on the administration building construction: plumbing work has begun and soil from the band's practice field was used to level the administration building pad after the band director requested field leveling.

Project manager Zach Mikulenka told trustees the project remains "on pace" to finish on schedule. The board asked administrative staff about schedule and field impacts; administration said they will continue to monitor timing and any disruption to school activities.