Summary
The May 4 board agenda included a Guaranteed Maximum Price No. 2 of $13,209,076 for Madden Elementary slab repairs (Millennium Project Solutions) and three sitework packages totaling roughly $13.25 million across three contractors; the items were listed for consideration and authorization.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
FORT BEND ISD — The Fort Bend ISD Board of Trustees reviewed multiple Bond 2023–related capital items at its May 4, 2026 called meeting, including a Guaranteed Maximum Price (GMP) No. 2 for Madden Elementary School slab repairs and upgrades. The agenda lists a GMP No. 2 with Millennium Project Solutions, Inc. for a not-to-exceed amount of $13,209,076 and seeks authorization for the superintendent to execute the GMP amendment.
The board packet also lists Construction Services Agreements for three sitework packages: Sitework Package 1 with E Contractors USA, LLC for $6,377,155; Sitework Package 2 with Prime Contractors, Inc. for $3,026,700; and Sitework Package 3 with M. Scott Construction, Inc. for $3,847,650. A job order contract with JR Thomas Group, Inc. to relocate and set up portable classroom buildings associated with Madden ES slab repairs was listed with a not-to-exceed contract amount of $600,000 and an associated design services agreement with MWA Architects. These expenditures were presented as items 'for consideration and approval' tied to Bond 2023 safety and security funds; the minutes do not record final approval votes in the provided text.