Board approves schematic design for junior high addition and new field house tied to proposed $26M bond

Gatesville ISD Board of Trustees · April 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Architects presented schematic renderings for a junior high addition and new field house; trustees approved moving to design development while consultants refine roof and HVAC cost estimates for the broader $26 million bond package.

Lead Huckabee Architect Mike Boyle presented the schematic design for the junior high addition and a new field house, and said the team will proceed to the design development phase if the board approves the schematics. Boyle noted that consultants are still examining the Intermediate roof and HVAC systems, so some cost estimates remain pending.

"We continue to have favorable estimates on the junior high and field house costs," Boyle told trustees. The board approved the schematic design and authorized staff and consultants to move to the next phase of work as Cloud Construction completes cost-evaluation tasks tied to the proposed $26 million bond package.