Board increases contingency for T.M. Clark Elementary bond project, authorizes General Fund use

Board of Trustees, GREGORY-PORTLAND ISD · March 30, 2026

Summary

The Board approved raising the Owner's Contingency for the Bond 2023 T.M. Clark Elementary School project from $1,252,342 to $2,252,342 and authorized budget amendments including use of General Fund balance; vote 7–0.

The Board voted to increase the Owner's Contingency for the Bond 2023 T.M. Clark Elementary School project from $1,252,342 (2.59% of the original GMP) to $2,252,342 (4.56% of the updated GMP) and authorized necessary budget amendments, including the use of General Fund balance to support the increase. Mark Roach made the motion; Nicole Nolen seconded and the motion carried 7–0.

Administration framed the change as necessary for schedule and completion risk mitigation on the new elementary project. The Board’s approval increases the contingency line item and directs budget adjustments to fund the change.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source