Village awards 2026 MFT pavement patching contract to Brothers Asphalt for $145,016.40
Summary
Brothers Asphalt was the lowest responsible bidder at $145,016.40 for the 2026 MFT pavement patching program; staff will adjust planned areas to keep the work within the $200,000 appropriation and the board approved the resolution.
Get email alerts on the Roads Maintenance topic
No spam. Unsubscribe anytime.
Public Works staff described the annual Motor Fuel Tax (MFT) pavement patching program and identified seven locations proposed for repairs. Bids opened July 14 and six bids were received; Brothers Asphalt submitted the lowest responsible bid at $145,016.40. Staff recommended awarding the construction contract to Brothers Asphalt and adjusting the planned patch areas to stay within the $200,000 appropriation the village set in December 2025.
"Brother Asphalt was the lowest submitted, responsible bidder at a $145,016.40," staff said. The board approved the resolution on a roll call vote (6–0). The project will be adjusted to match the available MFT appropriation and the contractor agreed to extend bid prices for additional pavement patching locations if required.
Funding and next steps: the village appropriated $200,000 of MFT funds for the program; staff will finalize the specific patch locations and manage the scope to stay at or below the appropriation.