Bensenville approves engineering contracts to begin York Road–CPKC grade separation project
Summary
The board approved two GFT Infrastructure contracts to start phase‑1 work on a multi‑year grade‑separation project at York Road and the CPKC crossings: a locally funded survey contract ($145,578) and a larger federally oriented phase‑1 contract ($2,752,223).
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
Bensenville officials described a multi‑phase grade separation project intended to reduce lengthy train delays at four crossings (York, Center, Addison and Church). Staff said a 2022 feasibility study estimated total project costs at about $56.6 million (in 2022 dollars) and that substantial grant funding would be required to complete construction.
Staff recommended splitting phase 1 into two contracts. Contract A (field survey and locally funded topographic work) was presented at $145,578 so the village could avoid an IDOT review delay. Contract B, which covers broader preliminary engineering and federal/NEPA requirements tied to grant funding, was presented at $2,752,223. "It is now time to start the phase 1 process," staff said; both contracts were approved by roll call. Staff warned that the federal/IDOT approval process could take nine months to a year.
Next steps: staff said field survey work for Contract A can begin once the contract is approved; Contract B work will proceed through the federal, NEPA and IDOT processes and will rely on grant awards to cover the larger engineering costs.