Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Transportation Infrastructure topic

No spam. Unsubscribe anytime.

Bensenville approves engineering contracts to begin York Road–CPKC grade separation project

Bensenville Village Board · July 29, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved two GFT Infrastructure contracts to start phase‑1 work on a multi‑year grade‑separation project at York Road and the CPKC crossings: a locally funded survey contract ($145,578) and a larger federally oriented phase‑1 contract ($2,752,223).

Bensenville officials described a multi‑phase grade separation project intended to reduce lengthy train delays at four crossings (York, Center, Addison and Church). Staff said a 2022 feasibility study estimated total project costs at about $56.6 million (in 2022 dollars) and that substantial grant funding would be required to complete construction.

Staff recommended splitting phase 1 into two contracts. Contract A (field survey and locally funded topographic work) was presented at $145,578 so the village could avoid an IDOT review delay. Contract B, which covers broader preliminary engineering and federal/NEPA requirements tied to grant funding, was presented at $2,752,223. "It is now time to start the phase 1 process," staff said; both contracts were approved by roll call. Staff warned that the federal/IDOT approval process could take nine months to a year.

Next steps: staff said field survey work for Contract A can begin once the contract is approved; Contract B work will proceed through the federal, NEPA and IDOT processes and will rely on grant awards to cover the larger engineering costs.