HPISD reports 90% of Bond 2024 projects scheduled for August completion; parking and turf projects extend into 2027

Highland Park Independent School District Board of Trustees · April 28, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Interim Assistant Superintendent Scott Drillette told the board that an estimated 90% of Bond 2024 projects are scheduled for completion by August 2026; the student parking expansion and turf practice field are tentatively scheduled for spring 2027.

Scott Drillette, interim assistant superintendent for business services, briefed trustees on Bond 2024 project timing and scope.

Drillette said roughly 90% of bond projects are scheduled for completion by August 2026, including the addition of the student parking lot at Grassmere field and the district bus lot. He said the student parking expansion north of Hyer Street and the turf practice field have a tentative completion date of spring 2027. Any surplus bond dollars will be allocated after approval by the Finance Committee.

The board did not take formal action on the update; the report was informational. The minutes do not include specific dollar amounts remaining or a detailed project-by-project schedule.