Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Bond Update topic
No spam. Unsubscribe anytime.
Board hears updates on Kaufman Middle School, KHS agricultural facility and Helen Edwards ECC bond projects
Summary
Construction and design updates were presented to trustees on the Kaufman Middle School and Kaufman High School agricultural facility; VLK presented plans and progress on the Helen Edwards Early Childhood Center as part of the 2024 bond program.
Get email alerts on the Bond Update topic
No spam. Unsubscribe anytime.
During the meeting, Jeremy Slipley of Pogue Construction updated the board on progress at Kaufman Middle School and on the Kaufman High School agricultural facility funded by the 2024 bond program. Presentations described current work and next steps in construction; specific schedule and budget details were provided in the presentation materials to trustees.
Marty Sims with VLK gave a focused presentation on the Helen Edwards Early Childhood Center project under the 2024 bond. Minutes record the presentation and indicate that project materials and plans will be available to trustees and the public as part of the bond program’s reporting process.
